September 2023 Construction Update

Northeast Metropolitan Regional Vocational High School

The NEMT project has fully mobilized for construction and has completed bulk tree clearing on the hilltop project site within non-jurisdictional areas. Construction within
the jurisdictional areas has remained at a standstill as the project awaits a Superseding Order of Condition from the Massachusetts Department of Environmental Protection.

The sitework subcontractor, J.R. Vinagro installed temporary site fencing, removed stumps, completed pre-drilling/probing, and cleared excess topsoil to allow for
upcoming blasting work scheduled to start on October 12, 2023.

Anyone interested in signing up for pre-blast notifications can contact Esta Falvey, Maine Drilling & Blasting at 508-478-0273.

Workforce Participation:
Total Hours September 2023: 3,630
Total Project Hours to Date: 7,647